Aircraft Carrier Enterprise Delivery Delayed by 18 Months, Says Navy
Citat:The future aircraft carrier USS Enterprise (CVN-80) will deliver a year and a half later than prior projections, according to the Navy.
The Ford-class carrier, which is currently under construction at HII’s Newport News Shipbuilding in Virginia, will deliver in September of 2029, 18 months later than its previous scheduled delivery date in March of 2028, according to the Navy’s Fiscal Year 2025 budget documents.
The documents cite “delays in material availability and industry/supply chain performance” as the reason for the schedule change.
In addition to delays to the CVN-80 delivery, Monday’s budget submission also disclosed the Navy’s decision to delay the purchase of its next aircraft carrier, CVN-82, from Fiscal Year 2028 to Fiscal Year 2030.